APACHE DAILY UPDATES -
VARANUS ISLAND PIPELINE INCIDENT
7 January Update
- Remobilisation of personnel for Varanus Island repair activities.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- The K11A and B compressor louvres are being repaired.
- The HJV liquids handling control valves are being repaired.
- There are 143 personnel on site.
6 January Update
- HJV pipe rack installation has been completed.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors have been completed.
- The K11A and B compressor louvres are being repaired.
- The HJV liquids handling control valves are being repaired.
- There are 83 personnel on site.
5 January Update
- Mobilizing equipment to progress commissioning of the 12” SGL.
- Repairs to the HJV flare pilots have been completed.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable has been completed.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- The K11A and B compressor louvres are being repaired.
- The fin fan belts on the K12 compressor have been replaced.
- Hot loop testing of HJV receiver and separator instrumentation has been completed.
- There are 83 personnel on site.
2 January Update
- Repairs to the HJV flare pilots are in progress.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- The K11A and B compressor louvres are being repaired.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 56 personnel on site.
31 December Update
- Repairs to the HJV flare pilots are in progress.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 66 personnel on site.
30 December Update
- Commenced re-mobilisation of personnel following Tropical Cyclone Billy.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 66 personnel on site.
29 December Update
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 39 personnel on site.
24 December Update
- Plant tie down and de-mobilisation operations in preparation for Tropical Cyclone Billy is in progress.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 39 personnel on site.
23 December Update
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 160 personnel on site.
22 December Update
- The HJV train 3 was shut down and the blending skid tie in was completed.
- The blending skid was purged, pressure tested and brought on line.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 160 personnel on site.
19 December Update
- Preparing to shut down HJV train 3 for blending skid tie in work.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 200 personnel on site.
18 December Update
- Preparing to shut down HJV train 3 for blending skid tie in work
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 215 personnel on site.
17 December Update
- Preparing to shut down HJV train 3 for blending skid tie in work
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 224 personnel on site.
16 December Update
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 223 personnel on site.
15 December Update
- The HJV ground flare ignition system has been commissioned and the flare is back in service.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 223 personnel on site.
12 December Update
- Repairs to the HJV ground flare ignition system are in progress.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 219 personnel on site.
11 December Update
- First sales from HJV train 3 achieved on 10 December.
- Commenced repairs to the HJV ground flare ignition system.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 222 personnel on site.
10 December Update
- HJV train 3 production has commenced with first sales expected 10 December.
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 224 personnel on site.
9 December Update
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- Regeneration of HJV train 3 of molecular sieve beds is in progress.
- Drying HJV train 3 has commenced.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 221 personnel on site.
8 December Update
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- Integrity inspections on HJV train 3 have been completed.
- Introduction of hydrocarbons into HJV train 3 has commenced.
- Regeneration of HJV train 3 of molecular sieve beds has commenced.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 226 personnel on site.
5 December Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Nitrogen purging of HJV train 3 has been completed.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 242 personnel on site.
4 December Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4A recovery operations have been completed.
- Phase 5 recovery operations have commenced.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 241 personnel on site.
3 December Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 236 personnel on site.
2 December Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 234 personnel on site.
1 December Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 238 personnel on site.
28 November Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 246 personnel on site.
27 November Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- Topside integrity inspections on Amine train 2 have been completed.
- There are 244 personnel on site.
26 November Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 230 personnel on site.
25 November Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipelines is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 230 personnel on site.
24 November Update
- HJV pipe rack installation is in progress.
- Hydro test of new HJV pipe work is in progress .
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- Hot loop testing of HJV receiver and separator instrumentation is in progress.
- There are 237 personnel on site.
21 November Update
- HJV pipe rack installation is in progress.
- Installation and testing of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 232 personnel on site.
20 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 232 personnel on site.
19 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 237 personnel on site.
18 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 239 personnel on site.
17 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The HJV train 3 hot oil system is being heated.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Replaced lube oil cooler belts and waste heat recovery unit switches on K12 compressor.
- Inspections of the K11A and 11B compressors in progress.
- There are 237 personnel on site.
14 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The HJV train 3 hot oil system is being heated.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 238 personnel on site.
13 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- The HJV train 3 hot oil system is being heated.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 249 personnel on site.
12 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Cable to the HJV flare area has been installed.
- Phase 4 tie-in isolations are continuing.
- The HJV train 3 hot oil system is being heated.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 249 personnel on site.
11 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Cable installation to HJV flare area is in progress.
- Phase 4 tie-in isolations are continuing.
- The HJV train 3 hot oil system is being heated.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- The K12 compressor seal has been replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 232 personnel on site.
10 November Update
- HJV pipe rack installation is in progress.
- Hydro testing and post weld heat treatment of HJV pipelines is in progress.
- Installation of new HJV cable is in progress.
- Cable installation to HJV flare area is in progress.
- Phase 4 tie-in isolations are continuing.
- Cold circulation in the HJV train 3 hot oil system is in progress.
- The pressure safety valves on HJV trains 1 and 2 are being replaced.
- The K12 compressor seal is being replaced.
- Inspections of the K11A and 11B compressors in progress.
- There are 232 personnel on site.
7 November Update
- HJV pipe rack installation is in progress.
- Hydro testing and post weld heat treatment of HJV pipelines is in progress.
- Installation of new HJV cable is in progress.
- Cable installation to HJV flare area is continuing.
- Phase 4 tie-in isolations are continuing.
- Cold circulation in the HJV train 3 hot oil system is in progress.
- The K12 compressor seal is being replaced.
- Installation of the K11A compressor gearbox is in progress.
- There are 232 personnel on site.
6 November Update
- HJV pipe rack installation is in progress.
- Hydro testing and post weld heat treatment of HJV pipelines is in progress.
- Installation of new HJV cable is in progress.
- Cable installation to HJV flare area is continuing.
- Phase 4 tie-in isolations are continuing.
- Cold circulation in the HJV train 3 hot oil system is in progress.
- The K12 compressor is undergoing inspection prior to start up.
- Installation of the K11A compressor gearbox is in progress.
- There are 245 personnel on site.
5 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Cable installation to HJV flare area is continuing.
- Phase 4 tie-in isolations are continuing.
- Cold circulation in the HJV train 3 hot oil system is in progress.
- The K12 compressor is being prepared for a water wash.
- Installation of the K11A compressor gearbox is in progress.
- There are 256 personnel on site.
4 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- Cable installation to HJV flare area is continuing.
- Cold circulation in the HJV train 3 hot oil system is in progress.
- The K12 compressor is being prepared for a water wash.
- Commenced installation of the K11A compressor gearbox.
- There are 246 personnel on site.
3 November Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- Cable installation to HJV flare area is continuing.
- Cold circulation in the HJV train 3 hot oil system is in progress.
- The K12 compressor has been purged with nitrogen.
- There are 250 personnel on site.
31 October Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- Cable installation to HJV flare area is continuing.
- Cold circulation in the HJV train 3 hot oil system is in progress.
- The K12 compressor is being prepared for nitrogen purging.
- There are 250 personnel on site.
30 October Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are in progress.
- Cable installation to HJV flare area is in progress.
- Nitrogen purging of the HJV train 3 hot oil system has been completed.
- Commenced cold circulation in the HJV train 3 hot oil system.
- There are 245 personnel on site.
29 October Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- Cable installation to HJV flare area is continuing.
- There are 238 personnel on site.
28 October Update
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Phase 4 tie-in isolations are continuing.
- Cable installation to HJV flare area is continuing.
- There are 233 personnel on site.
27 October Update
- Testing of the K12 compressor control valves has been completed
- The K12 after coolers have been re-instated.
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Re-fitting production safety valves to HJV train 3 has been completed.
- Phase 4 tie-in isolations being completed by operations.
- Cable installations to HJV flare area are ongoing.
- There are 227 personnel on site.
24 October Update
- Testing of the K12 compressor control valves continues.
- The K12 after coolers are being re-instated.
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Re-fitting production safety valves to HJV train 3 continues.
- Phase 4 tie-in isolations being completed by operations.
- Cable installations to HJV flare area are ongoing.
- There are 225 personnel on site.
23 October Update
- Testing of the K12 compressor control valves continues.
- The K12 after coolers are being re-instated.
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Re-fitting production safety valves to HJV train 3 continues.
- Phase 4 tie-in isolations being completed by operations.
- Cable installations to HJV flare area are ongoing.
- There are 216 personnel on site.
22 October Update
- Testing of the K12 compressor control valves continues.
- The K12 after coolers are being re-instated.
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Re-fitting production safety valves to HJV train 3 continues.
- Tie-in points and plant separation isolations for Phase 4 continues.
- Cable installations to HJV flare area are ongoing.
- There are 222 personnel on site.
21 October Update
- Testing of the K12 compressor control valves continues.
- The K12 after coolers are being re-instated.
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Re-fitting production safety valves to HJV train 3 continues.
- Tie-in points and plant separation isolations for Phase 4 continues.
- Cable installations to HJV flare area are ongoing.
- There are 212 personnel on site.
- Night shift set to start 21 st October.
20 October Update
- Testing of the K12 compressor control valves continues.
- The K12 after coolers are being re-instated.
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Re-fitting production safety valves to HJV train 3 continues.
- Tie-in points and plant separation isolations for Phase 4 continues.
- Cable installations to HJV flare area are ongoing.
- There are 205 personnel on site.
17 October Update
- Testing of the K12 compressor control valves continues.
- The K12 after coolers are being re-instated.
- HJV pipe rack installation is in progress.
- Installation of new HJV cable is in progress.
- Re-fitting production safety valves to HJV train 3 continues.
- Tie-in points and plant separation isolations for Phase 4 continues.
- Cable installations to HJV flare area are ongoing.
- There are 214 personnel on site.
16 October Update
- Testing of the K12 compressor control valves continues .
- The K12 after coolers are being re-instated.
- HJV pipe rack installation is in progress .
- Installation of new HJV cable is in progress .
- Re-fitting production safety valves to HJV train 3 continues .
- Tie-in points and plant separation isolations for Phase 4 continues.
- There are 214 personnel on site.
15 October Update
- Testing of the K12 compressor control valves continues
- The K12 after coolers have been dried
- HJV pipe rack installation is in progress
- Tie-in points and plant separation isolations for Phase 4 continues
- Installation of new HJV cable is in progress
- Re-fitting production safety valves to HJV train 3 is in progress
- There are 214 personnel on site.
14 October Update
- Testing of the K12 compressor control valves still underway
- The K12 after coolers are currently being dried
- HJV pipe rack installation is in progress
- Tie-in points and plant separation isolations for Phase 4 continues
- Installation of new HJV cable is in progress
- Re-fitting production safety valves to HJV train 3
- There are 200 personnel on site.
13th October Update
- Testing of the K12 compressor control valves still underway
- Hydro testing of K12 after coolers has been completed and drying of the coolers will commence today
- HJV pipe rack installation commenced
- Tie-in points and plant separation isolations for Phase 4 continues
- Commenced installation of new HJV cable
- Re-fitting production safety valves to HJV train 3
- There are 200 personnel on site.
10th October Update
- HJV valve calibrations and re-installation of production safety valves continuing
- Draining of HJV train 3 vessels is still underway
- K12 compressor waster heat recovery unit prepared for internal welding
- Testing of the K12 compressor control valves continues
- Removal of fire damaged cable in the HJV compressor area is ongoing
- Isolation of tie-in points and plant for Phase 4 continues
- There are 201 personnel on site.
9th October Update
- HJV valve calibrations and re-installation of production safety valves continuing
- Draining of HJV train 3 vessels is still underway
- Testing of the K12 compressor control valves continues
- Removal of fire damaged cable in the HJV compressor area is ongoing
- Isolation of tie-in points and plant for Phase 4 has commenced
- There are 201 personnel on site.
8th October Update
- HJV train 3 hot oil strainers have been re-instated
- HJV valve calibrations are ongoing
- Production safety valves are being re-installed
- Draining of the separators has been completed
- Testing of the K12 compressor control valves continues
- Preparing for pressure testing of the K12 compressor sales gas coolers
- There are 206 personnel on site.
7th October Update
- HJV train 3 filter support repaired and the dry gas filters were replaced
- The HJV train 3 hot oil strainers were removed and cleaned
- Draining of the HJV separators is continuing
- Testing of the K-12 compressor control valves is ongoing
- Testing of the sales gas after cooler fans and hot oil pumps continues
- Progressing with removal of fire damaged cable in the HJV compressor area
- There are 201 personnel on site.
6th October Update
- HJV train 3 hot loop testing of instruments and the fire and gas systems continues.
- Commenced draining HJV vessels and changing filters.
- Testing of the K-12 compressor control valves has commenced.
- Setting up for pressure testing of the K-12 compressor sales gas coolers.
- Cable installation in the train 3 hot oil skid area has commenced.
- Fire damaged cable is being removed in the HJV compressor area.
- There are 200 personnel on site.
3rd October Update
- Testing of K-12 compressor control valves is being conducted.
- Hot loop testing of HJV train 3, the K-12 compressor and fire and gas systems is continuing.
- Setting up for pressure testing of the K-12 sales gas coolers and HJV train 3 hot oil trim cooler
- Removal of the fire damaged cable in the HJV compressor area is continuing.
- There are 225 personnel on site.
2 October Update
- Fire damaged cable is being removed in the HJV compressor area.
- Cable installation in the HJV train 3 hot oil skid areas in ongoing.
- Hot loop testing of the HJV train 3 instruments and fire and gas systems is underway.
- Two repaired alternators have been scheduled for re-installation into the plant.
- There are 215 personnel on site.
1 October Update
- Harriet production header modifications commenced.
- Harriet manifold has been cold cut and flanges have been welded on.
- Harriet phase 4 production safety valve removal has been completed.
- There are 208 personnel on site.
30 September Update
- Phase 3 production safety valve removal completed.
- Phase 4 production safety valve removal is ongoing.
- The K-12 compressor 8000 hr electrical/instrumentation service was competed.
- The K-12 waste heat recovery unit damper actuator was changed out with a spare unit.
- There are 209 personnel on site.
26 September Update
- Commenced HJV production safety valve testing and certification.
- Completed 8000 hour mechanical service on the K-12 compressor.
- Started re-installation of pig receiver pipe work.
- There are 210 personnel on site.
25 September Update
- Hot loop testing of the HJV train 3 instruments and fire and gas systems are ongoing .
- Completed w elding flanges onto the ends of the 30” pipe spool removed from the load out line.
- Cable installation is ongoing in the HJV train 3 hot oil skid area.
- Set up for HJV production safety valve testing and certification.
- There are 214 personnel on site .
24 September Update
- Hot loop testing of the HJV train 3 instruments and fire and gas systems was conducted.
- Flanges were being welded onto the ends of the 30" pipe spool that was removed from the load out line.
- There are 219 personnel on site.
23 September Update
- Harriet compressor and waste heat recovery unit internal vessel inspections were carried out.
- Internal inspection of the HJV inlet diffuser began.
- The 30” load out pipeline spool was cold cut and removed from the plant. Flanges are to be welded to the spool sections.
- There are 218 personnel on site.
22 September Update
- Beach crossing pipe work is being painted and wrapped.
- Footings are being installed for beach pipe supports.
- H2S injection pump modification work completed.
- Hot loop testing was conducted on HJV train 3 instruments and fire and gas systems.
- HJV slug catcher internal inspections carried out. Damage to the internal coating will require repairs .
- There are 197 personnel on site.
19 September Update
- The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
- The sandblasting of the Harriet Joint Venture slug catchers is in progress.
- Repairs to the amine train 1 are in progress.
- There are 209 personnel on site.
18 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and train 3 hot oil skid is in progress.
- The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
- Commenced draining liquids from the Harriet Joint Venture hot oil header.
- The sandblasting of the Harriet Joint Venture slug catchers is in progress.
- There are 211 personnel on site.
17 September Update
- The damaged Harriet Joint Venture train 1 and 2 hot oil skids have been dismantled.
- The installation of the 6” pipeline spools on the beach has been completed.
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
- The sandblasting of the Harriet Joint Venture slug catchers is in progress.
- There are 210 personnel on site.
16 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- The hot oil pump on the Harriet Joint Venture Train 3 has been removed for internal inspection.
- The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
- The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
- The sandblasting of the Harriet Joint Venture slug catchers is in progress.
- The installation of 6” pipeline spools is in progress.
- There are 208 personnel on site.
15 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- The hot oil pump on the Harriet Joint Venture Train 3 has been removed for internal inspection.
- The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
- The Harriet Joint Venture trains 1 and 2 are being drained of liquids.
- The 12” sales gas line spool has been tied into the existing line.
- The installation of 6” pipeline spools is in progress.
- There are 191 personnel on site.
12 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
- The Harriet Joint Venture slug catchers are being sand blasted.
- The installation of 6” pipeline spools, along with excavation to allow for coating of field welds, is in progress.
- There are 185 personnel on site.
11 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
- The hydro test of a section of the 12” sales gas line is in progress.
- The installation of 6” pipeline spools is in progress, commenced excavation for to allow for coating of field welds.
- There are 189 personnel on site.
10 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
- The installation of 6” pipeline spools is in progress, commenced excavation for to allow for coating of field welds.
- There are 186 personnel on site.
9 September Update
- The East Spar train # 1 was re-started at 0100hrs on 9 September.
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress. The electric motors have been removed.
- The damaged Harriet Joint Venture train 1 and 2 hot oil skids are being dismantled.
- The line cap on the 12” sales gas line has been installed and is ready for the hydro test. The installation of 6” pipeline spools is in progress.
- There are 176 personnel on site.
8 September Update
- The East Spar train 1 remains offline for maintenance.
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress. The electric motors have been removed.
- The overhaul and pressure testing of shut down valves from the K12 compressor is in progress.
- Pipeline spools for the 12” infield line are being prepared.
- The electrical inspections on the Harriet Joint Venture Wonnich receiver skid are in progress.
- Hot oil is being drained from the Harriet Joint Venture train 1 and 2 skids.
- There are 184 personnel on site.
4 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- Shut down valves from the K12 compressor have been removed for overhaul and pressure testing.
- Pipeline spools for the 12” infield line are being prepared.
- The Harriet Joint Venture Wonnich receiver skid is undergoing an electrical inspection.
- There are 176 personnel on site.
3 September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- Shut down valves from the K12 compressor have been removed for overhaul and pressure testing.
- Pipeline spools for the 12” infield line are being prepared.
- There are 179 personnel on site.
2nd September Update
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- Shut down valves from the K12 compressor have been removed for overhaul and pressure testing.
- A hydro test is being conducted on the 12” sales gas line.
- There are 171 personnel on site.
1st September 2008
- The Amine train 1 has been commissioned and is currently online.
- Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
- A hydro test is being conducted on the 12” sales gas line.
- There are 178 personnel on site.
29th August 2008
- Commissioning of the Amine train 1 electrical and instrumentation systems are in progress.
- The electrical and instrumentation inspections on the Harriet Joint Venture K12 compressor are in progress.
- Commenced removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid.
- Replacement of the HJV electrical cable trays are in progress.
- The installation of the HJV pipe rack is in progress.
- Repairs on the 12” sales gas line are ongoing.
- There are 188 personnel on site.
28th August 2008
- Testing of the Amine train 1 motor has commenced.
- Electrical and instrumentation inspections on the HJV K-12 compressor are continuing.
- Replacement of the HJV electrical cable trays are in progress.
- The installation of the HJV pipe rack is in progress.
- Repairs on the 12” sales gas line are ongoing.
- There are 196 personnel on site.
27th August 2008
- Commissioning of t he Amine train 1 will commence today.
- Electrical and instrumentation inspections on the HJV K-12 compressor are continuing.
- Replacement of the HJV electrical cable trays is in progress.
- The installation of the HJV pipe rack is in progress.
- Repairs on the 12” sales gas line are ongoing.
- There are 204 personnel on site.
26th August 2008
- Electrical and instrumentation inspections on the HJV K-12 compressor are continuing.
- The installation of the HJV pipe rack is ongoing.
- Repairs on the 12” sales gas line are ongoing.
- There are 196 personnel on site.
25th August 2008
- East Spar train 1 has been returned to service.
- Electrical and instrumentation inspections have started on the HJV K-12 compressor.
- The installation of the HJV pipe rack is ongoing.
- Repairs on the 12” sales gas line are ongoing.
- There are 187 personnel on site.
22nd August 2008
- East Spar train 1 remains offline to change out the mercury guard bed.
- The 30” and 8” pipeline tie-ins have been completed.
- Repairs on the 12” sales gas line are ongoing.
- There are 190 personnel on site.
21st August 2008
- East Spar train 1 has been taken offline to change out the mercury guard bed.
- The 30” liquids loading pipeline is in position to complete welding activities.
- Installation of the new HJV pipe rack is continuing.
- There are 195 personnel on site.
20th August 2008
- Preparations to change the mercury guard bed on the East Spar train 1 are continuing.
- The East Spar train 1 surge drum spools have been installed.
- Welding of the 8” pipeline on the beach is continuing.
- Installation of the new HJV pipe rack is continuing.
- There are 194 personnel on site.
19th August 2008
- Commenced preparations to change the mercury guard bed on East Spar train 1.
- Welding of the 8” pipeline on the beach is continuing.
- Installation of the new HJV pipe rack is continuing.
- There are 192 personnel on site.
18th August 2008
- System integrity checks on all discharge pipework and 16” sales gas pipeline were conducted at 9,000 kPa.
- Commenced chilling East Spar train 2 at 12:00hrs on August 17.
- Commenced sales gas from East Spar train 2 at 16:00hrs on August 17.
- Commenced welding the first joint on the beach side of the 12” sales gas pipeline.
- Hydrotesting of the 30” liquids load out and 8” pipeline spools is continuing.
- Demolition of HJV pipe rack and coupon cutting is continuing.
- Installation of the new HJV pipe rack is continuing.
- There are 176 personnel on site.
15th August 2008
- The 30” liquids load out pipeline has been hydrotested.
- The 8” pipeline spools on the pipeline beach are to be hydrotested today.
- New East Spar train 2 pipework has been installed on the Stabiliser.
- East Spar train 2 is currently undergoing system integrity checks.
- Installation of the new HJV pipe rack has commenced.
- There are 199 personnel on site.
14th August 2008
- East Spar train 2 was purged with nitrogen over night.
- Installation of new East Spar train 2 pipework between the Stabiliser Surge drum and Stabiliser will commence this morning.
- Flange integrity checks on East Spar train 2 to be conducted following pipework installation.
- The 30” liquids load out pipeline is being filled for hydrotesting.
- There are 193 personnel on site.
13th August 2008
- The East Spar train 2 gas compressor fin fan motor was replaced.
- Instrument repairs on East Spar train 2 are continuing.
- East Spar train 2 nitrogen purging planned to start today.
- Welding of 30” liquids load out pipeline has commenced.
- There are 194 personnel on site.
12th August 2008
- Electrical system integrity tests on East Spar train 2 are continuing.
- Repairs to East Spar train 2 transmitters are continuing.
- Planning to replace East Spar train 2 gas compressor fin fan motor today.
- There are 191 personnel on site.
11th August 2008
- Electrical system integrity tests on East Spar train 2 are continuing.
- East Spar train 2 integrity testing continues on refurbished valves.
- There are 186 personnel on site.
8th August 2008
- Electrical system integrity tests on East Spar train 2 are continuing.
- East Spar train 1 mercury guard bed will require replacement when train 2 is returned to service.
- There are 173 personnel on site.
7th August 2008
- The meter at the Compressor Station 1 inlet point to the DBNGP was pressure tested and has been commissioned.
- Sales gas into the DBNGP commenced at 08:18AM 6th August.
- Electrical system integrity tests are being conducted on East Spar train 2.
- There are 159 personnel on site.
6th August 2008
- The Amine plant is currently being heated to operating temperature.
- The export sales gas carbon dioxide level is currently 0.1%.
- The pressure in the 16” export sales gas pipeline achieved 4000kpa.
- Gas is expected to be introduced into the DBNGP on 6 August.
- There are 158 personnel on site.
5th August 2008
- Drying of East Spar train 1 has been completed.
- Amine train 2 charge pumps have been commissioned and amine is now circulating.
- Commenced pressurising the 16” export sales gas pipeline at 16:30 on 4 August.
- 159 personnel on site.
4th August 2008
- East Spar phase 1 system integrity testing completed.
- East Spar phase 1 hot oil and glycol systems have been commissioned.
- East Spar power generation on line and supplying power for the whole island.
- Drying of East Spar train 1 has commenced.
- 141 personnel on site.
1st August 2008
- The East Spar slug catchers were pressure tested.
- The fuel gas system has been commissioned and is ready for start up.
- System checks on East Spar train #1 are continuing with 50% completed.
- It is currently forecast that gas supply into the WA domestic s ystem is expected to commence by 6th August.
31st July 2008
- Nitrogen purging of the East Spar facilities has been completed.
- Gas has been introduced into the East Spar plant.
- System checks of the East Spar slugcatchers and fuel gas system have been completed.
- There are 162 personnel on site.
30th July 2008
- Nitrogen purging of the processing facilities continues.
- The #2 amine train has been purged with nitrogen.
- Approval has been received to introduce hydrocarbons into the East Spar plant.
- Introduction of hydrocarbons has commenced with system checks to be conducted today.
- There are 162 personnel on site.
29th July 2008
- Nitrogen purging of the East Spar plant has commenced.
- Purging of the East Spar slugcatchers has been completed.
- Demolition of the HJV pipe rack is continuing.
- There are 156 personnel on site.
28th July 2008
- NOPSA phase 1 and 2 commissioning inspections were completed.
- Modification of the East Spar train #1 stabiliser surge drum has been completed.
- Close out of the East Spar train #1 hazardous area list is continuing.
- Re-coating of the 30" pipeline has been completed.
- Fire water ring main repairs were completed.
- There are 155 personnel on site.
25th July 2008
- NOPSA has commenced the phase 1 and 2 commissioning inspections.
- Close out of the East Spar train #1 hazardous area items is progressing.
- There are 184 personnel on site.
24th July 2008
- Nitrogen purging of the 16" pipeline has been completed.
- 16" pipeline shut down valve electrical & instrument air hookup has been completed.
- A flange has been welded onto the open end of the 12" export pipeline at the beach crossing.
- Demolition of the damaged pipe in the pipe rack near the new 16" pipeline is being undertaken.
- There are 191 personnel on site.
22nd July 2008
- East Spar plant de-isolation has started with the hot oil and fuel gas systems.
- Support work for the 16" pipeline is ongoing with rock bolt frames on the beach crossing being welded into place.
- Work on the 30" load out pipeline has been suspended to allow reapplication of pipeline coating.
- There are 197 personnel on site.
21st July 2008
- The 16" pipeline supports have been poured.
- Hydrotesting of the 16" pipeline on the beach side has been completed.
- Preparations have been made for the final 16" pipeline tie-in.
- The 30" load out pipeline double jointing has started on the beach crossing.
- Three pig receivers were removed from the demolition area.
- There are 191 personnel on site.
18th July 2008
- The 16" pipeline barred T was installed near the shutdown valve.
- The electrical cable ladder and instrument air line has been run to the 16" pipeline shutdown valve.
- All planned inspections have been completed by the vessel inspector.
- There are 203 personnel on site.
17th July 2008
- Welding of the 16" pipeline at the anchor block is progressing.
- The 12" pipeline has been excavated to the waters edge.
- All East Spar internal vessel inspections have been completed
- There are 203 personnel on site.
16th July 2008
- Excavation of the 12" pipeline back to the shoreline has been completed.
- A new East Spar elevated flare assembly has been installed.
- Removal of the mercury guard bed material is being undertaken to allow vessel inspections.
- There are 195 personnel on site.
15th July 2008
- Installation of the 16" pipeline continues.
- The plant side 16" pipeline repair was hydro tested.
- The East Spar elevated flare tip pilot pipe work hydro test was completed.
- There are 189 personnel on site.
14th July 2008
- Further progress made on the repair and refurbishment of East Spar train #2 production control valves.
- Electrical testing of the HJV and East Spar plants is continuing.
- The plant section of the 16" pipeline has been hydro tested.
- Coating of the 12" and 8" pipeline lengths continues.
- Installation of the new 16" pipeline section is progressing.
- The concrete support for the 16" pipeline shutdown valve has been poured.
- There are 190 personnel on site.
11th July 2008
- The 16" pipeline anchor block at the top of the beach slope has been backfilled and compacted.
- Coating is being applied to the 12" and 8" pipeline lengths.
- Electrical testing of the HJV and East Spar plants is ongoing.
- The East Spar train #2 tri-ethylene glycol contractor and coalescer were inspected.
- The amine plant hot oil and H2S scavenger unit tie-ins are continuing.
- Repair and refurbishment of the East Spar train #2 production control valves is progressing.
- There are 188 personnel on site.
10th July 2008
- 20 metres of 16" pipeline was positioned on the beach slope and the top bend was installed.
- Welding and x-ray testing of the 16" pipeline is progressing.
- Electrical testing of the HJV and East Spar plants is still underway.
- The East Spar train #2 low temperature separator was inspected.
- Tie-in of the hot oil and H2S scavenger units to the amine plant continues.
- Repair and refurbishment of the East Spar train #2 production control valves is progressing.
- There are 193 personnel on site.
9th July 2008
- All pipework in the rack through the receiver area has been cold cut except for the HJV train #3 inlet and flare header.
- Electrical testing of the HJV and East Spar plants is ongoing.
- The East Spar train #2 inlet separator and stabiliser reboiler internal inspections were completed.
- Internal scanning of the East Spar tube bundle is being conducted.
- The East Spar amine plant tie-ins have commenced.
- Production control valve re-certification has been completed.
- There are 202 personnel on site.
8th July 2008
- Positioning and welding of the 16" pipeline is progressing.
- The damaged HJV cable and cable tray have been removed from the receiver area.
- Electrical testing of the HJV and East Spar plants is ongoing.
- The East Spar train #2 inlet separator has been prepared for inspection.
- The East Spar amine train has been prepared for tie-in.
- Repair and refurbishment of the East Spar train #2 production control valves continues.
- There are 199 personnel on site.
7th July 2008
- Tie-in of the 16" pipeline has been completed in the plant rack and 16" pipe bends are being welded.
- The anchor block for the 16" pipeline has been poured.
- Removal of damaged HJV plant cable and the damaged cable tray is progressing.
- Electrical testing of the HJV and East Spar plants is still being conducted.
- Re-instatement of East Spar train #1 is continuing and external inspections of East Spar train #2 are 55% complete.
- External inspections of the East Spar amine plant have been completed.
- Repair and refurbishment of East Spar train #2 production control valves is continuing.
- There are 191 personnel on site.
3rd July 2008
- Demolition of the HJV pipe rack continues.
- The first joint of new 16" pipeline has been welded.
- Footings are being poured in the pipeline receiver area.
- Electrical testing of the HJV and East Spar plants is progressing.
- East Spar amine train external vessel inspections are continuing.
- Isolation of the interfaces between the HJV and ESJV plants is still underway.
- There are 210 personnel on site.
2nd July 2008
- Demolition of the HJV pipe rack is progressing.
- Footings for the 16" pipeline have been poured.
- Electrical testing of the HJV and East Spar plants is continuing.
- The East Spar slug catchers were re-instated and 74 internal inspections have been completed.
- Isolation of the interfaces between the HJV and ESJV plants continue.
- There are 198 personnel on site.
1st July 2008
- Demolition of the HJV pipe rack is progressing.
- Electrical testing of the HJV and East Spar plants is being conducted.
- East Spar train #1 production shutdown valves were re-instated.
- Damaged valves and instruments are being removed from the East Spar train #2.
- External vessel inspections on the East Spar amine trains are being undertaken.
- Isolation of the interfaces between the HJV and ESJV plants is still underway.
- NOPSA and DoIR teams are onsite to carry out inspections of the demolition and civil works on the 16" and 30" pipelines.
- There are 188 personnel on site.
30th June 2008
- The 8”, 16” and 30” pipelines have been removed from the beach area.
- A new section of 16” pipe has been moved into the beach area for positioning and installation.
- Isolation of the plant interfaces between the HJV and ESJV facilities is continuing.
- Removal of damaged valves and instrumentation from East Spar gas processing train #2 has commenced.
- Demolition of the HJV pipe rack is being undertaken.
- East Spar shutdown work continues with the internal inspection of 63 vessels completed.
- There are now 179 personnel on site.
27th June 2008
- The 6-inch and 30-inch lines were drained and removal of lines in the beach area is continuing.
- Six internal vessel inspections and three tube bundle surveys were completed.
- Preparation is under way for removal of damaged valves and instrumentation from East Spar gas processing train #2.
- Compressor Station #1 tie-ins were completed and production control valve refurbishment is continuing.
- There are 182 personnel on site.
26th June 2008
- Embankment prepared for installation of 16-inch pipeline.
- 173 personnel now engaged in on-site restoration efforts.
|