APACHE DAILY UPDATES -
VARANUS ISLAND PIPELINE INCIDENT

7 January Update

  • Remobilisation of personnel for Varanus Island repair activities.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • The K11A and B compressor louvres are being repaired.
  • The HJV liquids handling control valves are being repaired.
  • There are 143 personnel on site.

6 January Update

  • HJV pipe rack installation has been completed.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors have been completed.
  • The K11A and B compressor louvres are being repaired.
  • The HJV liquids handling control valves are being repaired.
  • There are 83 personnel on site.

5 January Update

  • Mobilizing equipment to progress commissioning of the 12” SGL.
  • Repairs to the HJV flare pilots have been completed.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable has been completed.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • The K11A and B compressor louvres are being repaired.
  • The fin fan belts on the K12 compressor have been replaced.
  • Hot loop testing of HJV receiver and separator instrumentation has been completed.
  • There are 83 personnel on site.

2 January Update

  • Repairs to the HJV flare pilots are in progress.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • The K11A and B compressor louvres are being repaired.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 56 personnel on site.

31 December Update

  • Repairs to the HJV flare pilots are in progress.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 66 personnel on site.

30 December Update

  • Commenced re-mobilisation of personnel following Tropical Cyclone Billy.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 66 personnel on site.

29 December Update

  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 39 personnel on site.

24 December Update

  • Plant tie down and de-mobilisation operations in preparation for Tropical Cyclone Billy is in progress.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 39 personnel on site.

23 December Update

  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 160 personnel on site.

22 December Update

  • The HJV train 3 was shut down and the blending skid tie in was completed.
  • The blending skid was purged, pressure tested and brought on line.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 160 personnel on site.

19 December Update

  • Preparing to shut down HJV train 3 for blending skid tie in work.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 200 personnel on site.

18 December Update

  • Preparing to shut down HJV train 3 for blending skid tie in work
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 215 personnel on site.

17 December Update

  • Preparing to shut down HJV train 3 for blending skid tie in work
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 224 personnel on site.

16 December Update

  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 223 personnel on site.

15 December Update

  • The HJV ground flare ignition system has been commissioned and the flare is back in service.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 223 personnel on site.

12 December Update

  • Repairs to the HJV ground flare ignition system are in progress.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 219 personnel on site.

11 December Update

  • First sales from HJV train 3 achieved on 10 December.
  • Commenced repairs to the HJV ground flare ignition system.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 222 personnel on site.

10 December Update

  • HJV train 3 production has commenced with first sales expected 10 December.
  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 224 personnel on site.

9 December Update

  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Regeneration of HJV train 3 of molecular sieve beds is in progress.
  • Drying HJV train 3 has commenced.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 221 personnel on site.

8 December Update

  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Integrity inspections on HJV train 3 have been completed.
  • Introduction of hydrocarbons into HJV train 3 has commenced.
  • Regeneration of HJV train 3 of molecular sieve beds has commenced.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 226 personnel on site.

5 December Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Nitrogen purging of HJV train 3 has been completed.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 242 personnel on site.

4 December Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4A recovery operations have been completed.
  • Phase 5 recovery operations have commenced.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 241 personnel on site.

3 December Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 236 personnel on site.

2 December Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 234 personnel on site.

1 December Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 238 personnel on site.

28 November Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 246 personnel on site.

27 November Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • Topside integrity inspections on Amine train 2 have been completed.
  • There are 244 personnel on site.

26 November Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 230 personnel on site.

25 November Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipelines is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 230 personnel on site.

24 November Update

  • HJV pipe rack installation is in progress.
  • Hydro test of new HJV pipe work is in progress .
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • Hot loop testing of HJV receiver and separator instrumentation is in progress.
  • There are 237 personnel on site.

21 November Update

  • HJV pipe rack installation is in progress.
  • Installation and testing of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 232 personnel on site.

20 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 232 personnel on site.

19 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 237 personnel on site.

18 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 239 personnel on site.

17 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The HJV train 3 hot oil system is being heated.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Replaced lube oil cooler belts and waste heat recovery unit switches on K12 compressor.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 237 personnel on site.

14 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The HJV train 3 hot oil system is being heated.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 238 personnel on site.

13 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The HJV train 3 hot oil system is being heated.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 249 personnel on site.

12 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Cable to the HJV flare area has been installed.
  • Phase 4 tie-in isolations are continuing.
  • The HJV train 3 hot oil system is being heated.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 249 personnel on site.

11 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Cable installation to HJV flare area is in progress.
  • Phase 4 tie-in isolations are continuing.
  • The HJV train 3 hot oil system is being heated.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • The K12 compressor seal has been replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 232 personnel on site.

10 November Update

  • HJV pipe rack installation is in progress.
  • Hydro testing and post weld heat treatment of HJV pipelines is in progress.
  • Installation of new HJV cable is in progress.
  • Cable installation to HJV flare area is in progress.
  • Phase 4 tie-in isolations are continuing.
  • Cold circulation in the HJV train 3 hot oil system is in progress.
  • The pressure safety valves on HJV trains 1 and 2 are being replaced.
  • The K12 compressor seal is being replaced.
  • Inspections of the K11A and 11B compressors in progress.
  • There are 232 personnel on site.

7 November Update

  • HJV pipe rack installation is in progress.
  • Hydro testing and post weld heat treatment of HJV pipelines is in progress.
  • Installation of new HJV cable is in progress.
  • Cable installation to HJV flare area is continuing.
  • Phase 4 tie-in isolations are continuing.
  • Cold circulation in the HJV train 3 hot oil system is in progress.
  • The K12 compressor seal is being replaced.
  • Installation of the K11A compressor gearbox is in progress.
  • There are 232 personnel on site.

6 November Update

  • HJV pipe rack installation is in progress.
  • Hydro testing and post weld heat treatment of HJV pipelines is in progress.
  • Installation of new HJV cable is in progress.
  • Cable installation to HJV flare area is continuing.
  • Phase 4 tie-in isolations are continuing.
  • Cold circulation in the HJV train 3 hot oil system is in progress.
  • The K12 compressor is undergoing inspection prior to start up.
  • Installation of the K11A compressor gearbox is in progress.
  • There are 245 personnel on site.

5 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Cable installation to HJV flare area is continuing.
  • Phase 4 tie-in isolations are continuing.
  • Cold circulation in the HJV train 3 hot oil system is in progress.
  • The K12 compressor is being prepared for a water wash.
  • Installation of the K11A compressor gearbox is in progress.
  • There are 256 personnel on site.

4 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • Cable installation to HJV flare area is continuing.
  • Cold circulation in the HJV train 3 hot oil system is in progress.
  • The K12 compressor is being prepared for a water wash.
  • Commenced installation of the K11A compressor gearbox.
  • There are 246 personnel on site.

3 November Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • Cable installation to HJV flare area is continuing.
  • Cold circulation in the HJV train 3 hot oil system is in progress.
  • The K12 compressor has been purged with nitrogen.
  • There are 250 personnel on site.

31 October Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • Cable installation to HJV flare area is continuing.
  • Cold circulation in the HJV train 3 hot oil system is in progress.
  • The K12 compressor is being prepared for nitrogen purging.
  • There are 250 personnel on site.

30 October Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are in progress.
  • Cable installation to HJV flare area is in progress.
  • Nitrogen purging of the HJV train 3 hot oil system has been completed.
  • Commenced cold circulation in the HJV train 3 hot oil system.
  • There are 245 personnel on site.

29 October Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • Cable installation to HJV flare area is continuing.
  • There are 238 personnel on site.

28 October Update

  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Phase 4 tie-in isolations are continuing.
  • Cable installation to HJV flare area is continuing.
  • There are 233 personnel on site.

27 October Update

  • Testing of the K12 compressor control valves has been completed
  • The K12 after coolers have been re-instated.
  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Re-fitting production safety valves to HJV train 3 has been completed.
  • Phase 4 tie-in isolations being completed by operations.
  • Cable installations to HJV flare area are ongoing.
  • There are 227 personnel on site.

24 October Update

  • Testing of the K12 compressor control valves continues.
  • The K12 after coolers are being re-instated.
  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Re-fitting production safety valves to HJV train 3 continues.
  • Phase 4 tie-in isolations being completed by operations.
  • Cable installations to HJV flare area are ongoing.
  • There are 225 personnel on site.

23 October Update

  • Testing of the K12 compressor control valves continues.
  • The K12 after coolers are being re-instated.
  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Re-fitting production safety valves to HJV train 3 continues.
  • Phase 4 tie-in isolations being completed by operations.
  • Cable installations to HJV flare area are ongoing.
  • There are 216 personnel on site.

22 October Update

  • Testing of the K12 compressor control valves continues.
  • The K12 after coolers are being re-instated.
  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Re-fitting production safety valves to HJV train 3 continues.
  • Tie-in points and plant separation isolations for Phase 4 continues.
  • Cable installations to HJV flare area are ongoing.
  • There are 222 personnel on site.

 

21 October Update  

  • Testing of the K12 compressor control valves continues.
  • The K12 after coolers are being re-instated.
  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Re-fitting production safety valves to HJV train 3 continues.
  • Tie-in points and plant separation isolations for Phase 4 continues.
  • Cable installations to HJV flare area are ongoing.
  • There are 212 personnel on site.
  • Night shift set to start 21 st October.

20 October Update  

  • Testing of the K12 compressor control valves continues.
  • The K12 after coolers are being re-instated.
  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Re-fitting production safety valves to HJV train 3 continues.
  • Tie-in points and plant separation isolations for Phase 4 continues.
  • Cable installations to HJV flare area are ongoing.
  • There are 205 personnel on site.

17 October Update  

  • Testing of the K12 compressor control valves continues.
  • The K12 after coolers are being re-instated.
  • HJV pipe rack installation is in progress.
  • Installation of new HJV cable is in progress.
  • Re-fitting production safety valves to HJV train 3 continues.
  • Tie-in points and plant separation isolations for Phase 4 continues.
  • Cable installations to HJV flare area are ongoing.
  • There are 214 personnel on site.

16 October Update

  • Testing of the K12 compressor control valves continues .
  • The K12 after coolers are being re-instated.
  • HJV pipe rack installation is in progress .
  • Installation of new HJV cable is in progress .
  • Re-fitting production safety valves to HJV train 3 continues .
  • Tie-in points and plant separation isolations for Phase 4 continues.
  • There are 214 personnel on site.

15 October Update

  • Testing of the K12 compressor control valves continues
  • The K12 after coolers have been dried
  • HJV pipe rack installation is in progress
  • Tie-in points and plant separation isolations for Phase 4 continues
  • Installation of new HJV cable is in progress
  • Re-fitting production safety valves to HJV train 3 is in progress
  • There are 214 personnel on site.

14 October Update

  • Testing of the K12 compressor control valves still underway
  • The K12 after coolers are currently being dried
  • HJV pipe rack installation is in progress
  • Tie-in points and plant separation isolations for Phase 4 continues
  • Installation of new HJV cable is in progress
  • Re-fitting production safety valves to HJV train 3
  • There are 200 personnel on site.

13th October Update

  • Testing of the K12 compressor control valves still underway
  • Hydro testing of K12 after coolers has been completed and drying of the coolers will commence today
  • HJV pipe rack installation commenced
  • Tie-in points and plant separation isolations for Phase 4 continues
  • Commenced installation of new HJV cable
  • Re-fitting production safety valves to HJV train 3
  • There are 200 personnel on site.

10th October Update

  • HJV valve calibrations and re-installation of production safety valves continuing
  • Draining of HJV train 3 vessels is still underway
  • K12 compressor waster heat recovery unit prepared for internal welding
  • Testing of the K12 compressor control valves continues
  • Removal of fire damaged cable in the HJV compressor area is ongoing
  • Isolation of tie-in points and plant for Phase 4  continues
  • There are 201 personnel on site.

9th October Update

  • HJV valve calibrations and re-installation of production safety valves continuing
  • Draining of HJV train 3 vessels is still underway
  • Testing of the K12 compressor control valves continues
  • Removal of fire damaged cable in the HJV compressor area is ongoing
  • Isolation of tie-in points and plant for Phase 4 has commenced
  • There are 201 personnel on site.

8th October Update

  • HJV train 3 hot oil strainers have been re-instated
  • HJV valve calibrations are ongoing
  • Production safety valves are being re-installed
  • Draining of the separators has been completed
  • Testing of the K12 compressor control valves continues
  • Preparing for pressure testing of the K12 compressor sales gas coolers
  • There are 206 personnel on site.

7th October Update

  • HJV train 3 filter support repaired and the dry gas filters were replaced
  • The HJV train 3 hot oil strainers were removed and cleaned
  • Draining of the  HJV separators is continuing
  • Testing of the K-12 compressor control valves is ongoing
  • Testing of the sales gas after cooler fans and hot oil pumps continues
  • Progressing with removal of fire damaged cable in the HJV compressor area
  • There are 201 personnel on site.

6th October Update

  • HJV train 3 hot loop testing of instruments and the fire and gas systems continues.
  • Commenced draining HJV vessels and changing filters.
  • Testing of the K-12 compressor control valves has commenced.
  • Setting up for pressure testing of the K-12 compressor sales gas coolers.
  • Cable installation in the train 3 hot oil skid area has commenced.
  • Fire damaged cable is being removed in the HJV compressor area.
  • There are 200 personnel on site.

3rd October Update

  • Testing of K-12 compressor control valves is being conducted.
  • Hot loop testing of HJV train 3, the K-12 compressor and fire and gas systems is continuing.
  • Setting up for pressure testing of the K-12 sales gas coolers and HJV train 3 hot oil trim cooler
  • Removal of the fire damaged cable in the HJV compressor area is continuing.
  • There are 225 personnel on site.

2 October Update

  • Fire damaged cable is being removed in the HJV compressor area.
  • Cable installation in the HJV train 3 hot oil skid areas in ongoing.
  • Hot loop testing of the HJV train 3 instruments and fire and gas systems is underway.
  • Two repaired alternators have been scheduled for re-installation into the plant.
  • There are 215 personnel on site.

1 October Update

  • Harriet production header modifications commenced.
  • Harriet manifold has been cold cut and flanges have been welded on.
  • Harriet phase 4 production safety valve removal has been completed.
  • There are 208 personnel on site.

30 September Update

  • Phase 3 production safety valve removal completed.
  • Phase 4 production safety valve removal is ongoing.
  • The K-12 compressor 8000 hr electrical/instrumentation service was competed.
  • The K-12 waste heat recovery unit damper actuator was changed out with a spare unit.
  • There are 209 personnel on site.

26 September Update

  • Commenced HJV  production safety valve testing and certification.
  • Completed 8000 hour mechanical service on the K-12 compressor.
  • Started re-installation of pig receiver pipe work.
  • There are 210 personnel on site.

25 September Update

  • Hot loop testing  of the HJV train 3 instruments and fire and gas systems are ongoing .
  • Completed  w elding flanges onto  the ends of  the 30” pipe spool removed from  the load out line.
  • Cable installation  is ongoing in  the HJV train 3 hot oil skid area.
  • Set up for HJV  production safety valve testing and certification.
  • There are 214 personnel on site .

24 September Update   

  • Hot loop testing of the HJV train 3 instruments and fire and gas systems was conducted.  
  • Flanges were being welded onto the ends of the 30" pipe spool that was removed from the load out line. 
  • There are 219 personnel on site.

23 September Update   

  • Harriet compressor and waste heat recovery unit internal vessel inspections were carried out.  
  • Internal inspection of the HJV inlet diffuser began. 
  • The 30” load out pipeline spool was cold cut and removed from the plant. Flanges are to be welded to the spool sections.
  • There are 218 personnel on site.

22 September Update

  • Beach crossing pipe work is being painted and wrapped.
  • Footings are being installed for beach pipe supports.
  • H2S injection pump modification work completed.
  • Hot loop testing was conducted on HJV train 3 instruments and fire and gas systems.
  • HJV slug catcher internal inspections carried out. Damage to the internal coating will require repairs .
  • There are 197 personnel on site.

19 September Update

  • The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
  • The sandblasting of the Harriet Joint Venture slug catchers is in progress.
  • Repairs to the amine train 1 are in progress.
  • There are 209 personnel on site.

18 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and train 3 hot oil skid is in progress. 
  • The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
  • Commenced draining liquids from the Harriet Joint Venture hot oil header.
  • The sandblasting of the Harriet Joint Venture slug catchers is in progress.
  • There are 211 personnel on site.

17 September Update

  • The damaged Harriet Joint Venture train 1 and 2 hot oil skids have been dismantled.
  • The installation of the 6” pipeline spools on the beach has been completed.
  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress. 
  • The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
  • The sandblasting of the Harriet Joint Venture slug catchers is in progress.
  • There are 210 personnel on site.

16 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress. 
  • The hot oil pump on the Harriet Joint Venture Train 3 has been removed for internal inspection.
  • The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
  • The Harriet Joint Venture trains 1, 2 and 3 are being drained of liquids.
  • The sandblasting of the Harriet Joint Venture slug catchers is in progress.
  • The installation of 6” pipeline spools is in progress.
  • There are 208 personnel on site.

15 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress. 
  • The hot oil pump on the Harriet Joint Venture Train 3 has been removed for internal inspection.
  • The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
  • The Harriet Joint Venture trains 1 and 2 are being drained of liquids.
  • The 12” sales gas line spool has been tied into the existing line.
  • The installation of 6” pipeline spools is in progress.
  • There are 191 personnel on site.

12 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
  • The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
  • The Harriet Joint Venture slug catchers are being sand blasted.
  • The installation of 6” pipeline spools, along with excavation to allow for coating of field welds, is in progress.
  • There are 185 personnel on site.

11 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
  • The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
  • The hydro test of a section of the 12” sales gas line is in progress.
  • The installation of 6” pipeline spools is in progress, commenced excavation for to allow for coating of field welds.
  • There are 189 personnel on site.

10 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
  • The damaged Harriet Joint Venture train 1 and 2 hot oil skids are continuing to be dismantled.
  • The installation of 6” pipeline spools is in progress, commenced excavation for to allow for coating of field welds.
  • There are 186 personnel on site.

9 September Update

  • The East Spar train # 1 was re-started at 0100hrs on 9 September.
  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.  The electric motors have been removed.
  • The damaged Harriet Joint Venture train 1 and 2 hot oil skids are being dismantled.
  • The line cap on the 12” sales gas line has been installed and is ready for the hydro test.  The installation of 6” pipeline spools is in progress.
  • There are 176 personnel on site.

8 September Update

  • The East Spar train 1 remains offline for maintenance.
  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.  The electric motors have been removed.
  • The overhaul and pressure testing of shut down valves from the K12 compressor is in progress.
  • Pipeline spools for the 12” infield line are being prepared.
  • The electrical inspections on the Harriet Joint Venture Wonnich receiver skid are in progress.
  • Hot oil is being drained from the Harriet Joint Venture train 1 and 2 skids.
  • There are 184 personnel on site.

4 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
  • Shut down valves from the K12 compressor have been removed for overhaul and pressure testing.
  • Pipeline spools for the 12” infield line are being prepared.
  • The Harriet Joint Venture Wonnich receiver skid is undergoing an electrical inspection.
  • There are 176 personnel on site.

3 September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
  • Shut down valves from the K12 compressor have been removed for overhaul and pressure testing.
  • Pipeline spools for the 12” infield line are being prepared.
  • There are 179 personnel on site.

2nd September Update

  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
  • Shut down valves from the K12 compressor have been removed for overhaul and pressure testing.
  • A hydro test is being conducted on the 12” sales gas line.
  • There are 171 personnel on site.

1st September 2008

  • The Amine train 1 has been commissioned and is currently online.
  • Removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid is in progress.
  • A hydro test is being conducted on the 12” sales gas line.
  • There are 178 personnel on site.

29th August 2008

  • Commissioning of the Amine train 1 electrical and instrumentation systems are in progress.
  • The electrical and instrumentation inspections on the Harriet Joint Venture K12 compressor are in progress.
  • Commenced removal of damaged cabling on the Harriet Joint Venture K12 compressor and Train 3 hot oil skid.
  • Replacement of the HJV electrical cable trays are in progress.
  • The installation of the HJV pipe rack is in progress.
  • Repairs on the 12” sales gas line are ongoing.
  • There are 188 personnel on site.

28th August 2008

  • Testing of the Amine train 1 motor has commenced.
  • Electrical and instrumentation inspections on the HJV K-12 compressor are continuing.
  • Replacement of the HJV electrical cable trays are in progress.
  • The installation of the HJV pipe rack is in progress.
  • Repairs on the 12” sales gas line are ongoing.
  • There are 196 personnel on site.

27th August 2008

  • Commissioning of t he Amine train 1 will commence today.
  • Electrical and instrumentation inspections on the HJV K-12 compressor are continuing.
  • Replacement of the HJV electrical cable trays is in progress.
  • The installation of the HJV pipe rack is in progress.
  • Repairs on the 12” sales gas line are ongoing.
  • There are 204 personnel on site.

26th August 2008

  • Electrical and instrumentation inspections on the HJV K-12 compressor are continuing.
  • The installation of the HJV pipe rack is ongoing.
  • Repairs on the 12” sales gas line are ongoing.
  • There are 196 personnel on site.

25th August 2008

  • East Spar train 1 has been returned to service.
  • Electrical and instrumentation inspections have started on the HJV K-12 compressor.
  • The installation of the HJV pipe rack is ongoing.
  • Repairs on the 12” sales gas line are ongoing.
  • There are 187 personnel on site.

22nd August 2008

  • East Spar train 1 remains offline to change out the mercury guard bed.
  • The 30” and 8” pipeline tie-ins have been completed.
  • Repairs on the 12” sales gas line are ongoing.
  • There are 190 personnel on site.

21st August 2008

  • East Spar train 1 has been taken offline to change out the mercury guard bed.
  • The 30” liquids loading pipeline is in position to complete welding activities.
  • Installation of the new HJV pipe rack is continuing.
  • There are 195 personnel on site.

20th August 2008

  • Preparations to change the mercury guard bed on the East Spar train 1 are continuing.
  • The East Spar train 1 surge drum spools have been installed.
  • Welding of the 8” pipeline on the beach is continuing.
  • Installation of the new HJV pipe rack is continuing.
  • There are 194 personnel on site.

19th August 2008

  • Commenced preparations to change the mercury guard bed on East Spar train 1.
  • Welding of the 8” pipeline on the beach is continuing.
  • Installation of the new HJV pipe rack is continuing.
  • There are 192 personnel on site.

18th August 2008

  • System integrity checks on all discharge pipework and 16” sales gas pipeline were conducted at 9,000 kPa.
  • Commenced chilling East Spar train 2 at 12:00hrs on August 17.
  • Commenced sales gas from East Spar train 2 at 16:00hrs on August 17.
  • Commenced welding the first joint on the beach side of the 12” sales gas pipeline.
  • Hydrotesting of the 30” liquids load out and 8” pipeline spools is continuing.
  • Demolition of HJV pipe rack and coupon cutting is continuing.
  • Installation of the new HJV pipe rack is continuing.
  • There are 176 personnel on site.

15th August 2008

  • The 30” liquids load out pipeline has been hydrotested.
  • The 8” pipeline spools on the pipeline beach are to be hydrotested today.
  • New East Spar train 2 pipework has been installed on the Stabiliser.
  • East Spar train 2 is currently undergoing system integrity checks.
  • Installation of the new HJV pipe rack has commenced.
  • There are 199 personnel on site.

14th August 2008

  • East Spar train 2 was purged with nitrogen over night.
  • Installation of new East Spar train 2 pipework between the Stabiliser Surge drum and Stabiliser will commence this morning.
  • Flange integrity checks on East Spar train 2 to be conducted following pipework installation.
  • The 30” liquids load out pipeline is being filled for hydrotesting.
  • There are 193 personnel on site.

13th August 2008

  • The East Spar train 2 gas compressor fin fan motor was replaced.
  • Instrument repairs on East Spar train 2 are continuing.
  • East Spar train 2 nitrogen purging planned to start today.
  • Welding of 30” liquids load out pipeline has commenced.
  • There are 194 personnel on site.

12th August 2008

  • Electrical system integrity tests on East Spar train 2 are continuing.
  • Repairs to East Spar train 2 transmitters are continuing.
  • Planning to replace East Spar train 2 gas compressor fin fan motor today.
  • There are 191 personnel on site.

11th August 2008

  • Electrical system integrity tests on East Spar train 2 are continuing.
  • East Spar train 2 integrity testing continues on refurbished valves.
  • There are 186 personnel on site.

8th August 2008

  • Electrical system integrity tests on East Spar train 2 are continuing.
  • East Spar train 1 mercury guard bed will require replacement when train 2 is returned to service.
  • There are 173 personnel on site.

7th August 2008

  • The meter at the Compressor Station 1 inlet point to the DBNGP was pressure tested and has been commissioned.
  • Sales gas into the DBNGP commenced at 08:18AM 6th August.
  • Electrical system integrity tests are being conducted on East Spar train 2.
  • There are 159 personnel on site.

6th August 2008

  • The Amine plant is currently being heated to operating temperature.
  • The export sales gas carbon dioxide level is currently 0.1%.
  • The pressure in the 16” export sales gas pipeline achieved 4000kpa.
  • Gas is expected to be introduced into the DBNGP on 6 August.
  • There are 158 personnel on site.

5th August 2008

  • Drying of East Spar train 1 has been completed.
  • Amine train 2 charge pumps have been commissioned and amine is now circulating.
  • Commenced pressurising the 16” export sales gas pipeline at 16:30 on 4 August.
  • 159 personnel on site.

4th August 2008

  • East Spar phase 1 system integrity testing completed.
  • East Spar phase 1 hot oil and glycol systems have been commissioned.
  • East Spar power generation on line and supplying power for the whole island.
  • Drying of East Spar train 1 has commenced.
  • 141 personnel on site.

1st August 2008

  • The East Spar slug catchers were pressure tested.
  • The fuel gas system has been commissioned and is ready for start up.
  • System checks on East Spar train #1 are continuing with 50% completed.
  • It is currently forecast that gas supply into the WA domestic  s ystem  is expected to commence by 6th August.

31st July 2008

  • Nitrogen purging of the East Spar facilities has been completed.
  • Gas has been introduced into the East Spar plant.
  • System checks of the East Spar slugcatchers and fuel gas system have been completed.
  • There are 162 personnel on site.

30th July 2008

  • Nitrogen purging of the processing facilities continues.
  • The #2 amine train has been purged with nitrogen.
  • Approval has been received to introduce hydrocarbons into the East Spar plant.
  • Introduction of hydrocarbons has commenced with  system checks to be conducted today.
  • There are 162 personnel on site.

29th July 2008

  • Nitrogen purging of the East Spar plant has commenced.
  • Purging of the East Spar slugcatchers has been completed.
  • Demolition of the HJV pipe rack is continuing.
  • There are 156 personnel on site.

28th July 2008

  • NOPSA phase 1 and 2 commissioning inspections were completed.
  • Modification of the East Spar train #1 stabiliser surge drum has been completed.
  • Close out of the East Spar train #1 hazardous area list is continuing.
  • Re-coating  of the 30" pipeline has been completed.
  • Fire water ring main repairs were completed.
  • There are 155 personnel on site.

25th July 2008

  • NOPSA has commenced the phase 1 and 2 commissioning inspections.
  • Close out of the East Spar train #1 hazardous area items is progressing.
  • There are 184 personnel on site.

24th July 2008

  • Nitrogen purging of the 16" pipeline has been completed.
  • 16" pipeline shut down valve electrical & instrument air hookup has been completed.
  • A flange has been welded onto the open end of the 12" export pipeline at the beach crossing.
  • Demolition of the damaged pipe in the pipe rack near the new 16" pipeline is being undertaken.
  • There are 191 personnel on site.

22nd July 2008

  • East Spar plant de-isolation has started with the hot oil and fuel gas systems.
  • Support work for the 16" pipeline is ongoing with rock bolt frames on the beach crossing being welded into place.
  • Work on the 30" load out pipeline has been suspended to allow reapplication of pipeline coating.
  • There are 197 personnel on site.

21st July 2008

  • The 16" pipeline supports have been poured.
  • Hydrotesting of the 16" pipeline on the beach side has been completed.
  • Preparations have been made for the final 16" pipeline tie-in.
  • The 30" load out pipeline double jointing has started on the beach crossing.
  • Three pig receivers were removed from the demolition area.
  • There are 191 personnel on site.

18th July 2008

  • The 16" pipeline barred T was installed near the shutdown valve.
  • The electrical cable ladder and instrument air line has been run to the 16" pipeline shutdown valve.
  • All planned inspections have been completed by the vessel inspector.
  • There are 203 personnel on site.

17th July 2008

  • Welding of the 16" pipeline at the anchor block is progressing.
  • The 12" pipeline has been excavated to the waters edge.
  • All East Spar internal vessel inspections have been completed
  • There are 203 personnel on site.

16th July 2008

  • Excavation of the 12" pipeline back to the shoreline has been completed.
  • A new East Spar elevated flare assembly has been installed.
  • Removal of the mercury guard bed material is being undertaken to allow vessel inspections.
  • There are 195 personnel on site.

15th July 2008

  • Installation of the 16" pipeline continues.
  • The plant side 16" pipeline repair was hydro tested.
  • The East Spar elevated flare tip pilot pipe work hydro test was completed.
  • There are 189 personnel on site.

14th July 2008

  • Further progress made on the repair and refurbishment of East Spar train #2 production control valves.
  • Electrical testing of the HJV and East Spar plants is continuing.
  • The plant section of the 16" pipeline has been hydro tested.
  • Coating of the 12" and 8" pipeline lengths continues.
  • Installation of the new 16" pipeline section is progressing.
  • The concrete support for the 16" pipeline shutdown valve has been poured.
  • There are 190 personnel on site.

11th July 2008

  • The 16" pipeline anchor block at the top of the beach slope has been backfilled and compacted.
  • Coating is being applied to the 12" and 8" pipeline lengths.
  • Electrical testing of the HJV and East Spar plants is ongoing.
  • The East Spar train #2 tri-ethylene glycol contractor and coalescer were inspected.
  • The amine plant hot oil and H2S scavenger unit tie-ins are continuing.
  • Repair and refurbishment of the East Spar train #2 production control valves is progressing.
  • There are 188 personnel on site.

10th July 2008

  • 20 metres of 16" pipeline was positioned on the beach slope and the top bend was installed.
  • Welding and x-ray testing of the 16" pipeline is progressing.
  • Electrical testing of the HJV and East Spar plants is still underway.
  • The East Spar train #2 low temperature separator was inspected.
  • Tie-in of the hot oil and H2S scavenger units to the amine plant continues.
  • Repair and refurbishment of the East Spar train #2 production control valves is progressing.
  • There are 193 personnel on site.

9th July 2008

  • All pipework in the rack through the receiver area has been cold cut except for the HJV train #3 inlet and flare header.
  • Electrical testing of the HJV and East Spar plants is ongoing.
  • The East Spar train #2 inlet separator and stabiliser reboiler internal inspections were completed.
  • Internal scanning of the East Spar tube bundle is being conducted.
  • The East Spar amine plant tie-ins have commenced.
  • Production control valve re-certification has been completed.
  • There are 202 personnel on site.

8th July 2008

  • Positioning and welding of the 16" pipeline is progressing.
  • The damaged HJV cable and cable tray have been removed from the receiver area.
  • Electrical testing of the HJV and East Spar plants is ongoing.
  • The East Spar train #2 inlet separator has been prepared for inspection.
  • The East Spar amine train has been prepared for tie-in.
  • Repair and refurbishment of the East Spar train #2 production control valves continues.
  • There are 199 personnel on site.
7th July 2008
  • Tie-in of the 16" pipeline has been completed in the plant rack and 16" pipe bends are being welded.
  • The anchor block for the 16" pipeline has been poured.
  • Removal of damaged HJV plant cable and the damaged cable tray is progressing.
  • Electrical testing of the HJV and East Spar plants is still being conducted.
  • Re-instatement of East Spar train #1 is continuing and external inspections of East Spar train #2 are 55% complete.
  • External inspections of the East Spar amine plant have been completed.
  • Repair and refurbishment of East Spar train #2 production control valves is continuing.
  • There are 191 personnel on site.
3rd July 2008
  • Demolition of the HJV pipe rack continues.
  • The first joint of new 16" pipeline has been welded.
  • Footings are being poured in the pipeline receiver area.
  • Electrical testing of the HJV and East Spar plants is progressing.
  • East Spar amine train external vessel inspections are continuing.
  • Isolation of the interfaces between the HJV and ESJV plants is still underway.
  • There are 210 personnel on site.
2nd July 2008
  • Demolition of the HJV pipe rack is progressing.
  • Footings for the 16" pipeline have been poured.
  • Electrical testing of the HJV and East Spar plants is continuing.
  • The East Spar slug catchers were re-instated and 74 internal inspections have been completed.
  • Isolation of the interfaces between the HJV and ESJV plants continue.
  • There are 198 personnel on site.
1st July 2008
  • Demolition of the HJV pipe rack is progressing.
  • Electrical testing of the HJV and East Spar plants is being conducted.
  • East Spar train #1 production shutdown valves were re-instated.
  • Damaged valves and instruments are being removed from the East Spar train #2.
  • External vessel inspections on the East Spar amine trains are being undertaken.
  • Isolation of the interfaces between the HJV and ESJV plants is still underway.
  • NOPSA and DoIR teams are onsite to carry out inspections of the demolition and civil works on the 16" and 30" pipelines.
  • There are 188 personnel on site.
30th June 2008
  • The 8”, 16” and 30” pipelines have been removed from the beach area.
  • A new section of 16” pipe has been moved into the beach area for positioning and installation.
  • Isolation of the plant interfaces between the HJV and ESJV facilities is continuing.
  • Removal of damaged valves and instrumentation from East Spar gas processing train #2 has commenced.
  • Demolition of the HJV pipe rack is being undertaken.
  • East Spar shutdown work continues with the internal inspection of 63 vessels completed.
  • There are now 179 personnel on site.
27th June 2008
  • The 6-inch and 30-inch lines were drained and removal of lines in the beach area is continuing.
  • Six internal vessel inspections and three tube bundle surveys were completed.
  • Preparation is under way for removal of damaged valves and instrumentation from East Spar gas processing train #2.
  • Compressor Station #1 tie-ins were completed and production control valve refurbishment is continuing.
  • There are 182 personnel on site.
26th June 2008
  • Embankment prepared for installation of 16-inch pipeline.
  • 173 personnel now engaged in on-site restoration efforts.